TNCPA §208(e): No Expansion on After-Acquired Property


In our last post, we discussed two of the principal exceptions to the Tennessee Non-Conforming Property Act, Tenn. Code Ann. §13-7-208, specifically subsections (f) and (j). To summarize, the act simply doesn’t apply to a premier type resort city (Gatlinburg), nor do subsections (g), (h), and (i) apply to home rule municipalities. A list of those home roominess Pawleys is included with the last post.

In a similar vein, this post will briefly discuss a significant restriction on the generally favorable treatment given non-conforming properties by the act. That restriction is found at TNCPA §208(e), which reads as follows:

Subsections (b)-(d) apply only to land owned and in use by such affected business, and do not operate to permit expansion of existing industry or business through the acquisition of additional land.

Therefore, while a non-conforming property is permitted to continue, including replacement and repairs, as desired under subsection (b)(1); to expand, including the construction of additional facilities under subsection (c); and to destroy and rebuild under subsection (d)(1); the continuation, expansion, or reconstruction cannot take place on after a acquired property. Once the property becomes legally non-conforming, purchase of any additional property cannot be used in a manner which expands the non-conforming activities.

There is a case directly on point. 421 Corporation v Metro Nashville, 36 SW 3d 469 (Tenn. Ct. App. 2000), involves the proposed expansion of an adult entertainment establishment (“The Purple Onion”) located at 2807 Nolensville Road in Nashville. The owner had purchased some additional property adjacent to the Purple Onion and wanted to expand the operations of the establishment into the adjacent buildings. The city refused issue a permit, and on appeal to the Metro Board of Zoning Appeals, the denial was upheld. An appeal was taken to Davidson County Chancery Court where the zoning board decision was affirmed, and the same result was obtained before the Tennessee Court of Appeals.

The owner’s argument was that his application was made pursuant to the Metro Zoning Ordinance and its language was less restrictive than the state statute. Judge Koch, writing for the court, concluded that the territorial restriction was mandatory and that even if the local ordinance could be interpreted so as to permit such an expansion it conflicted with the state statute and was not permissible. As a result, the decision of the lower court and the zoning board were both upheld.

As a final footnote, this subsection (e) was part of the original 1973 Tennessee Non-Conforming Property Act. The original act was comprised, generally speaking, of what is now §208 (b)(1), (c), (d)(1), and (e). In addition, with regard to both subsections (b) and (d), additional language was later added which necessitated new numbered paragraphs. In each instance, the retained paragraph became (1), and the new language is included in the paragraph marked (2). In the case of subsection (b), the newly added language deals with off-premise signs and in the case of subsection (d), the newly added language deals with multifamily residential land use.

In our next post, we’ll take a look at a couple of provisions of the act which are not used all that often.

Friday, May 17, 2013

TNCPA §208 (f) and (j): Special Exemptions


We have now reviewed the three main sections of the Tennessee Non-Conforming Property Act, Tenn. Code Ann. §13-7-208 (b)-(d). There is one additional section of great importance subsection (g), but we will defer discussion of that subsection for a few posts.

Today we will talk about two subsections which provide exemptions from the applicability of the statute. Sections 208 (f) and (j) are special provisions limiting the local governments to which the statute applies. Section 208(f) makes clear that sections (b)-(e) do not apply to “premier type tourist resorts” as defined by Tenn. Code Ann. §67-6-103 (a) (3) (B). Mainly, this means that those sections do not apply to Gatlinburg.

Section 208 (j) limits the applicability of subsections (g), (h) & (i) so that they do not apply to home rule municipalities. We will discuss the substantive impact of those subsections soon, but for now they relate mainly to discontinuation of the non-conforming property. There are few home rule municipalities here in Tennessee and they include some of the biggest cities in the state such as Memphis, Knoxville, and Chattanooga. Metro Nashville is a consolidated form of government but not home rule so that the limit does not apply to Nashville.  Of course, a home rule city may opt in to those provisions by action of its local legislative body. The other home rule municipalities are as follows:

Clinton
East Ridge
Etowah
Johnson City
Lenoir City
Mt. Juliet
Oak Ridge
Red Bank
Sevierville
Sweetwater
Whitwell

This list is from the Municipal Technical Advisory Service (MTAS) website which can be found here.

Of course, these exemptions just make the application and enforcement of the statute that much more difficult.

There is another interesting question with regard to this subsection (j). Can a home rule municipality opt in to only one of these three subsections, or if it intends to opt in, must it opt in and accept all three? This is important because subsection (i) specifically requires that any structure rebuilt on the property must conform to the bulk regulations. It might be helpful for a home rule municipality to opt in regarding subsection (i) if you did not also have to accept the complexities of subsection (g). The same is true with regard to subsection (h) which limits the expansion of a billboard. But, if the home rule municipality must accept all three together, that makes the decision quite a bit harder. Generally speaking, both subsections (h) and (i) place restrictions on expansion and reconstruction. Subsection (g) seems to limit their applicability as we will describe in a future post. But if you could adopt subsection (h) and (i) without adopting subsection (g), that might be a favorable position for a home rule municipality. In that way, the municipality would get the limitations on expansion and reconstruction, but not have to deal with the complexities and confusion which seemed to surround subsection (g).

In our next entry, we will briefly discuss TNCPA §208 (e), which restricts expansion of any non-conforming  property  beyond the land at the time the property became non-conforming.

Thursday, May 16, 2013

Funeral Homes & Crematoria


New construction of crematoria, either as an accessory to an existing funeral home or freestanding, continues to be controversial. Last month, in Loudon, Tennessee, an application for a special exception for a crematorium was deferred by the local zoning board. Recently, Knoxville adopted tighter restrictions on operation and placement of crematoria. There been several instances of requests in and around Nashville which have raised neighborhood concerns.

Knoxville’s new regulations made most existing crematoria legally non-conforming. It also evidently had the effect of allowing an existing funeral home to add a crematorium.

Certainly, requests for cremation services are on the increase in the funeral industry. Regulations which adequately protect surrounding land uses from adverse impact are obviously worthwhile. However, much of the concern may be attributable more to actual operations rather than external impact. Regulations of the internal operation are best left to the state agencies charged with that responsibility.

Take a look at the recent news article found here.

Wednesday, May 15, 2013

TNCPA §208 (d): Demolition/Reconstruction of NCFPs


We’ve been discussing, over the last week or so, the Tennessee Non-Conforming Property Act, Tenn. Code Ann. §13-7-208 (TNCPA). Last time we considered the expansion of a non-conforming property under §208 (c); in this post, we will take a look at the demolition/reconstruction of a non-conforming property under §208 (d).

Section 208 (d) allows the destruction and reconstruction of any structures on the non-conforming property. There is one important additional requirement that is not present in either §208 (b) or (c), and that is that the demolition/reconstruction must be “necessary to the conduct” of the commercial or industrial business. Under certain circumstances then, it may be best simply to expand under §208 (c) rather than destroy/reconstruct under §208 (d); sometimes business necessity is difficult to prove. Further, guidance from the courts has not been clear on what constitutes business necessity for this purpose. I believe that the business necessity test should be leniently construed, otherwise it actually encourages the property owner to expand the business rather than tear down and reconstruct. Let’s take a quick example.

If I have a business that makes widgets and I’d like to tear down my building and build a new one to improve efficiency and output, I would normally have to show business necessity under §208 (d). But suppose I simply decide to build a new building and leave the first one standing (assuming I have sufficient room on the property). I use the new building to make my widgets, and convert the original building to office and storage space. I submit that this expansion is permitted under §208 (c), and I need not make any showing of business necessity under §208 (d). But in effect, my business has expanded more than I actually needed, and to the extent that any case can be made that the use of the property is inconsistent with the surrounding land uses, the situation is probably even worse than if I had torn down the original building and replaced it with another. Thus perhaps a lenient position with regard to business necessity is called for.

Furthermore, under §208 (i), not only must the demolition and reconstruction be necessary for the continuation of the business, but in addition, the reconstructed facilities must comply with the bulk regulations contained in the zoning ordinance. Section 208 (i) expressly mentions setbacks, height, bulk, or requirements as to the physical location of a structure upon the site as existing zoning regulations which must be met if reconstructed under subsection (d). Again, compliance with these bulk regulations is often difficult and frequently the best advice is to simply expand under subsection (c) as opposed to reconstructing under subsection (d). Remember that under subsection (d), the reconstructed buildings must meet the bulk regulations. But under subsection (c), any additional facilities constructed do not need to meet the bulk regulations, and only in fact need to avoid becoming a nuisance. Obviously, the latter is a much lower standard to meet.

There is an express exception concerning off-site signs in subsection (i); the bulk regulations do not apply to reconstructed off-premise signs. There remains a significant question in my mind as to whether this distinction is constitutionally reasonable. It seems difficult to come up with an explanation as to why an off-site sign need not comply with the bulk regulations when another structure, such as, for example, an on-site sign does.

But perhaps my constitutional concern is groundless. Perhaps §208 (i) doesn’t really apply in the first place. Take a look at the final proviso of subsection (g)(4) which provides in part: the restrictions of subsection (i) shall apply only “if the property owner intentionally and voluntarily abandons the non-conforming use of the property.”  It is difficult to make any sense of this whatsoever. Subsection (g) (4) deals with discontinuation clauses and we will discuss it in detail in a later post. Why suddenly, at the end of the subsection, there is a reference to subsection (i) is hard to fathom. Furthermore, subsection (i) would ordinarily require that a property demolished and then reconstructed comply with the bulk regulations. Yet subsection (g) indicates that if the owner does not intentionally abandon the use, subsection (i) is inapplicable.

Seemingly, this makes no sense. If the property owner has demolished the structures on the property with the intent of rebuilding pursuant to subsection (d), then there is certainly no present intent to voluntarily abandon the non-conforming property. Yet, if there is no such intent, subsection (i) seems inapplicable. If that is true, then when would it ever apply?

Or is it possible that the statutory intent was that subsection (i) applied only after some period of inactivity. Again, that doesn’t help us much. If that’s the answer, then any owner wishing to invoke the protection of the statute and remove the restrictions of subsection (i), would simply cease operations for a few days or months and then begin the reconstruction process. If inactivity is necessary in order to invoke the proviso, that is easily done and once again it simply undermines the entire intent behind subsection (i).  

One other interesting comment is worth noting here. Let’s assume for a moment that the use of the property was permitted but the regulations which changed had only to do with the location of the structure on the property, that is, the bulk regulations were changed. For example, perhaps the local government now requires a greater setback from the street, or a larger side yard. Assume further that the non-conforming activity stops, perhaps because of a fire rendering the interior of the building unusable. The owner intends to demolish and reconstruct the entire building but allows it to sit for a year before applying for a building permit. Does subsection (i) permit the reconstruction of the building at the same location in violation of the bulk regulations? It would appear not. Even under subsection (g)(4)’s final proviso, the bulk regulations do not apply only if the property owner abandons the non-conforming use of the property. Since the use of the property in this hypothetical actually conforms, it would appear that the bulk regulations apply to the new construction. These are some very strange and convoluted statutory provisions. Hopefully, the courts will at some point give us additional instruction and how they are to be applied.

In the meantime, we can say that with regard to §208 (d) a non-conforming property can be demolished/reconstructed if the reconstructed facilities are necessary to the continuation of the business. It may be that the reconstructed buildings must comply with the bulk regulations of the local zoning ordinance, although this is unclear. Furthermore, it is certainly true that the destruction/reconstruction of an off-site sign need not comply with the local bulk regulations, but that any expansion of an off-site sign (under §208 (c) or (d)) must comply with the provisions of §208 (h) regarding the permitted size of any expansion.

Tuesday, May 14, 2013

TNCPA §208(c): Expanding NCFPs & Constructing new facilities


We’ve been talking about the Tennessee Non-Conforming Property Act, Tenn. Code Ann. §13-7-208, and in our last post, we talked specifically about §208 (b) which allows a non-conforming property to continue its non-conforming activities. Today, we’ll take a look at §208 (c), which allows non-conforming property to expand its operations and even construct additional facilities so long as there is no change in the use of the property.

Section 208 (c) allows the expansion of the non-conforming property, including the construction of additional facilities as desired for expansion. It is important to note that under this subsection, there is no requirement that the expanded facilities comply with other bulk regulations such as front, side, and rear setbacks. The expansion may go so far as desired so long as it does not create a nuisance to adjoining landowners. So, to the extent that there may be other regulations in the zoning ordinance which might restrict the expansion, those do not apply. This provision specifically prevents a local government from denying a building permit when a commercial or industrial business seeks to expand its current operations.

There is one important restriction on this right to expand: under §208 (h) off-site signs are not permitted to expand beyond certain dimensions specified in the statute. This section does make clear that the protective provisions of the act do apply to off-site signs, and it even defines such signs as “any sign that advertises or gives direction to any business, product, service, attraction or any other purpose or interest, other than the industrial, commercial or other business establishment located on the site where the sign is located.” Thus if you represent a sign interest, these restrictions are of significant importance.

Since §208 (h) limits only the size of off-site signs, presumably the expansion of an on-site sign is permitted without limitation, so long as the sign does not need to be destroyed and entirely rebuilt (see §208 (d) which we will discuss in our next entry). For example, if the structure holding the sign face aloft remains, and the sign face is replaced with a larger sign face, this would appear to be an expansion under §208 (c), and no matter how much larger the sign face of the on-site sign happens to be, it is permitted (unless it’s so big that it causes a nuisance to adjoining property owners).

Let’s take another example of the application of this section of the statute. Assume that you own a funeral home and while at the time of its initial construction, the property was owned for that use, the zoning is now changed in the mortuary is legally non-conforming. However, you want to expand the services provided by the funeral home by including cremation, which means that you will have to add a crematorium. Unfortunately, the local zoning ordinance does not allow a crematorium in the zoning district where you are located, just as it doesn’t allow the funeral home itself. In fact, a crematorium is permitted only in the industrial zoning district in your city. Does §208 (c) allow the expansion of the funeral home by the construction of a crematorium? It does.
Clearly, the funeral home is a commercial business establishment and also clearly under the terms of our hypothetical, it was in operation and permitted operate before the zoning changed making it legally non-conforming. Under those circumstances, §208 (c) says that the commercial business establishment “shall be allowed to expand operations and construct additional facilities which involve an actual continuance and expansion of the activities of the… business which were permitted and being conducted prior to the change in zoning…” Given the language of the statute, the only remaining question would be whether the construction of a crematorium involves a continuation and expansion of the mortuary services. Probably no one would disagree but that cremation is a mortuary service and thus the expansion is permitted. This is exactly what happened in BMC Enterprises v Mt. Juliet,  273 S.W. 3d 619 (Tenn. App. 2008; perm app den Oct 27, 2008). This case is interesting not just because it is a good example of the application of §208 (c), but in addition it involves what would seem to be a fairly significant expansion in the operations of the mortuary and significant construction of additional facilities. Finally, this was all done in the face of an outright prohibition by the city zoning regulations .

Finally, I cannot be emphasized enough that the expansion in business operations and construction of additional facilities must all relate to the same business use. If the use changes as a byproduct of the construction of additional facilities, then §208 provides no protection. A good example of this was a bed-and-breakfast in Winchester, Tenn., which applied for and received permission to expand its operations ostensibly to allow for modest dining facilities for guests and friends. The expansion however turned out to be a bar with live entertainment. The Tennessee Court of Appeals had no difficulty whatsoever in concluding that §208 offered no protection in the face of the change in use. Lafferty v Winchester, 46 S.W. 3d 752 (Tenn. App. 2000).


One final issue that is worthy of investigation here is by what standard is the land use evaluated. For example, in the Mt. Juliet case, should we look to the local zoning regulations to determine what a funeral home is, or should some other standard apply? The courts really haven’t reached a decision with regard to this issue, although in BMC Enterprises, the court did note that the local zoning regulations did not have a definition of funeral home, and as a result it looked to Tennessee state law for a definition.

Some land uses are defined in § 208 itself, such as the definition of off-site signs in §208 (h). Certainly it seems to me that since the Non-Conforming Property Act applies across the entire state of Tennessee (with certain limited statutory exemptions which we will review in a post later in this series), that there should be general definitions applicable across the state and not grounded in local zoning provisions. Otherwise, and expansion which is permitted in Mt. Juliet might not be permitted in Gallatin. Surely, this state limitation on local zoning powers should apply across local government boundaries to allow commercial and industrial businesses to continue operation, expand operations, and destroy and rebuild their facilities in like manner no matter where they are located. I’m sure that the Tennessee appellate courts will address this issue sometime in the not-too-distant future and will get an answer to this somewhat perplexing question.